Bug 4203 - Internal replication operations performed synchronously due to WorkManager bug
: Internal replication operations performed synchronously due to WorkManager bug
Status: RESOLVED FIXED
: Data Replication
Data Replication Service
: unspecified
: PC All
: P3 major
: ---
Assigned To:
:
:
: 4204
:
  Show dependency treegraph
 
Reported: 2006-02-07 15:42 by
Modified: 2006-02-22 17:05 (History)


Attachments


Note

You need to log in before you can comment on or make changes to this bug.


Description From 2006-02-07 15:42:00
Due to a bug in the WorkManager default implementation, replication operations
will be performed synchronously -- the initial thread that serviced the request
gets reused to perform all operations thus blocking things up.
------- Comment #1 From 2006-02-08 16:36:50 -------
Don't know how I assigned that incorrectly originally...